Collapsed As-Built Analysis: Step-by-Step Practical Guidance

Updated: Jun 29

The Collapsed As-Built (CAB) analysis is a retrospective "cause and effect" methodology used to determine how delay events impacted project completion. Unlike other methodologies that build delays into a programme, CAB starts with the actual as-built schedule and progressively removes delay events to determine their impact.


  1. Develop As-Built Programme

If no as-built programme exists, reconstruct it using available contemporaneous records. This should accurately reflect what actually happened during the project execution.


  1. Insert Logic Links

Add appropriate logic links between programme activities. Ideally, these links should be based on contemporaneous documents or witness statements rather than assumptions.


  1. Add Delay Events

Insert identified delay events into the as-built programme and link them to the appropriate as-built activities they affected.


  1. Remove Delay Events Sequentially

Remove delay events (or set to zero-day duration) in reverse chronological order, starting with the latest event and working backwards.


  1. Reschedule and Compare

After removing each delay event, reschedule the programme to demonstrate the earlier completion date that would have occurred without that delay event.


  1. Measure Impact

Compare completion dates before and after each delay event removal. The difference represents the critical delay attributable to that specific event.


  1. Repeat Process

Continue removing delay events one by one until all have been removed, measuring the impact of each.


Advantages and Disadvantages

Advantages

  • Relies upon factual as-built records

  • Simple and easy to understand

  • Persuasive as the estimated outcomes are based on facts

  • Ideal when no baseline or an unreliable baseline programme is available


Disadvantages

  • Time-consuming to produce the as-built programme

  • Difficult to identify contemporaneous critical path switch points

  • Only produces results when delay events are on the longest path

  • Challenging to recreate logic links retrospectively


The CAB methodology is particularly useful for assessing the effect of alleged acts of negligence or breaches to determine when a project would have been completed "but for" the negligent act or breach of contract, or to determine the extent of contractor culpable delay to support an assessment of concurrency. However, depending on jurisdiction and contract terms, it may not always be appropriate for assessing Extension of Time entitlement.


Require Assistance with a Claim or Dispute?

Just get in touch for a no-obligation complimentary review of any claim or dispute.


Contact

Mark Holden-Smith

07834284308

Comentários


bottom of page